O PROJEKTU
PROJEKT “IZGRADNJA TERMINALA ZA PRETOVAR RASUTIH TERETA U LUCI OSIJEK - KK.07.3.1.01.0001
Naziv projekta: “Izgradnja terminala za pretovar rasutih tereta u luci Osijek”
Ukupna vrijednost projekta: 34.413.522,60 EUR
EU sufinanciranje: 25.440.890,40 EUR
Bespovratna sredstva iz Državnog proračuna: 4.489.568,89 EUR
Naziv korisnika: JU Lučka uprava Osijek, K.F. Šepera 6, Osijek
Razdoblje provedbe projekta: od 10.05.2017 do 31.12.2023
Project name: “Construction of a bulk cargo transshipment terminal in the port of Osijek”
Total value of the project: EUR 34,413,522.60 EU co-financing: EUR 25,440,890.40 Grants from the State Budget: EUR 4,489,568.89 Name of user: JU Port Authority Osijek, K.F. Šepera 6, Osijek Project implementation period: from 10.05.2017 to 31.12.2023
Stara luka u Osijeku, gdje je bio terminal za rasute terete, stavljena je izvan funkcije 2015. godine. Lučke djelatnosti su preseljene na novu lokaciju u neurbaniziranom dijelu grada s ciljem bolje kvalitete života i zaštite okoliša.
Projekt Izgradnja terminala za pretovar rasutih tereta u luci Osijek obuhvaća:
- Izgradnju cca 240 m obalne građevine s 2 veza,
- Pretovarne uređaje za ukrcaj/iskrcaj i transport opreme (usipni koš s pretovarnim uređajima),
- Izgradnju pristupne ceste cca 300 m duljine,
- Izgradnju željezničkih kolosijeka cca 610m duljine,
- Izgradnju kranskih staza i ceste cca 285 m duljine,
- Izgradnju usipnog koša dimenzije 14,8×8,6×7,8 m
- Izgradnju trafostanice
- izgradnja potrebne infrastrukture (opskrba vodom i odvodnja, opskrba električnom energijom i rasvjeta, otvoreno skladište)
Projekt ima za cilj smanjiti prometno zagađenje u centru Osijeka, smanjiti mogućnost ekoloških incidenata u urbanom dijelu grada, povećati prometnu dostupnost Osječko-baranjske županije te osigurati pružanje lučkih usluga pretovara tereta na jedinstvenoj lokaciji.
Opći ciljevi projekta su:
- Podizanje razine zaštite okoliša pri prekrcaju tereta,
- Povećanje sigurnosti brodova u luci,
- Poboljšanje dostupne lučke infrastrukture,
- Razvoj efikasnog intermodalnog transporta tereta,
- Smanjenje operativnih troškova korištenjem nove opreme i tehnologije.
Strateški ciljevi projekta su:
- Povećanje udjela prometa unutarnjim plovnim putovima u odnosu na cestovni i željeznički promet,
- Revitalizacija gospodarstva u Osječko-baranjskoj županiji,
- Ravnomjeran razvoj regija u Republici Hrvatskoj i EU,
- Poboljšanje prometne produktivnosti i intermodalnih kapaciteta,
- Privlačenje novih industrija, dodane vrijednosti i industrijskog razvoja.
Projekt u skladu sa strateškim dokumentima:
- Strategija prometnog razvitka Republike Hrvatske (2017-2030)
- Strategija razvitka riječnog prometa u Republici Hrvatskoj za razdoblje od 2022-2032. godine
- Srednjoročni plan razvitka vodnih putova, luka i pristaništa Republike Hrvatske za razdoblje od 2022 do 2031. godine
- Akcijski plan za provedbu Srednjoročnog plana za razdoblje 2022-2024. godine
- Master plan razvitka luke Osijek
_______
The old port in Osijek, where there was a bulk cargo terminal, was decommissioned in 2015. Port activities were moved to a new location in a non-urbanized part of the city with the aim of better quality of life and environmental protection.
The project Construction of a bulk cargo transshipment terminal in the port of Osijek includes:
- Construction of approx. 240 m of coastal construction with 2 berths,
- Reloading devices for loading/unloading and transporting equipment (loading basket with transloading devices),
- Construction of an access road approx. 300 m long,
- Construction of railway tracks approx. 610m long,
- Construction of crane paths and road approx. 285 m long,
- Construction of a suction basket with dimensions of 14.8×8.6×7.8 m
- Construction of a substation
- construction of the necessary infrastructure (water supply and drainage, electricity supply and lighting, open storage
The project aims to reduce traffic pollution in the center of Osijek, reduce the possibility of environmental incidents in the urban part of the city, increase the traffic accessibility of the Osijek-Baranja County, and ensure the provision of port cargo handling services at a unique location.
The general goals of the project are:
- Raising the level of environmental protection during cargo handling,
- Increasing the safety of ships in the port,
- Improvement of available port infrastructure,
- Development of efficient intermodal freight transport,
- Reduction of operating costs by using new equipment and technology.
The strategic goals of the project are:
- Increasing the share of inland waterway traffic compared to road and rail traffic,
- Revitalization of the economy in Osijek-Baranja County,
- Balanced development of regions in the Republic of Croatia and the EU,
- Improving traffic productivity and intermodal capacities,
- Attracting new industries, added value and industrial development.
Project in accordance with strategic documents:
- Transport Development Strategy of the Republic of Croatia (2017-2030)
- Strategy for the development of river traffic in the Republic of Croatia for the period from 2022-2032. years
- Medium-term plan for the development of waterways, ports and piers of the Republic of Croatia for the period from 2022 to 2031
- Action plan for the implementation of the Medium-Term Plan for the period 2022-2024. years
- Osijek port development master plan